Q: P alone can do a piece of work in 24 days. The time taken by P to complete one-third of work is equal to time taken by Q to complete half of the work. How many days are required to complete by P and Q working together ? |
A. | 9 3/5 days |
B. | 7 days |
C. | 6 3/7 days |
D. | 8 days |
Answer» B. 7 days | |