Q: P alone can complete a piece of work in 6 days. Work done by Q alone in one day is equal to one-third of the work done by P alone in one day. In how many days can the work be completed if P and Q work together ? |
A. | 5 (2/3) |
B. | 6 (3/4 ) |
C. | 4 (1/2) |
D. | 3 |
Answer» D. 3 | |