				| 1. | 
                                    Q: K can lay Highway road between two cities in 16 days. L can do the same job in 12 days. With the help of M, they completes the job in 4 days. How much days does it take for M alone to complete the work ? | 
                            
| A. | 47/7 days | 
| B. | 59/6 days | 
| C. | 48/5 days | 
| D. | 57/5 days | 
| Answer» D. 57/5 days | |