                                    Q: K can build a wall in 30 days. L can demolish that wall in 60 days. If K and L work on alternate days, when will the wall be completed ? | 
                            
| A. | 120 days | 
| B. | 119 days | 
| C. | 118 days | 
| D. | 117 days | 
| Answer» E. | |