                                    Q: After working for 8 days, Hari Ram finds that only 1/3 rd of the work has been done. He employs Satya who is 60% as efficient as Hari Ram. How many days more would Satya take to complete the work ? | 
                            
| A. | 24 1/2 days | 
| B. | 25 3/2 days | 
| C. | 24 2/3 days | 
| D. | 26 2/3 days | 
| Answer» E. | |