				| 1. | 
                                    Q: After working for 8 days, Arun finds that only 13 rd of the work has been done. He employs Akhil who is 60% as efficient as Arun. How many days more would Akhil take to complete the work? | 
                            
| A. | 24.5 days | 
| B. | 26.6 days | 
| C. | 25 days | 
| D. | 20 days | 
| Answer» C. 25 days | |