Q: A contractor undertakes to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged so that the work may finish in time ?

A. 50
B. 48
C. 56
D. 64
Answer» D. 64