MCQOPTIONS
Saved Bookmarks
1. |
Q: A contractor undertake to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged so that the work may finish in time ? |
A. | 64 |
B. | 62 |
C. | 58 |
D. | 56 |
Answer» E. | |