Q: A contract is to be completed in 50 days and 105 men were set to work, each working 8 hour a day. After 25 days, 2/5th of the work is finished. How many additional men be employed, so that the work may be completed on time, each man now working 9 hour a day?

A. 34
B. 36
C. 35
D. 37
Answer» D. 37