1.

Q: A constructor estimates that 4 people can paint Mr. Karthik's house in 6 days. If he uses 5 people instead of 4, how long will they take to complete the job ?

A. 3 days
B. 26/3 days
C. 13/4 days
D. 24/5 days
Answer» E.