Q: A can do a piece of work in 14 days which B can do in 21 days. The begin together but 3 days before the completion of the work, A leaves off. The total number of days to complete the work is…… |
A. | 6.6 |
B. | 8.5 |
C. | 10.2 |
D. | 13.5 |
Answer» D. 13.5 | |