1.

Q: A can do a piece of work in 15 days and B can do it in 16 days and C can do it 24 days. They started the work together and A leaves after 3 days and B leaves after 4 days from the beginning. How long will work lost ?

A. 10 2/3 days
B. 13 1/5 days
C. 12 2/3 days
D. 11 5/7 days
Answer» C. 12 2/3 days