Q: A can do a piece of work in 15 days and B can do it in 16 days and C can do it 24 days. They started the work together and A leaves after 3 days and B leaves after 4 days from the beginning. How long will work lost ? |
A. | 10 2/3 days |
B. | 13 1/5 days |
C. | 12 2/3 days |
D. | 11 5/7 days |
Answer» C. 12 2/3 days | |