Q: A can do a certain job in 12 days. B is 60% more efficient than A. The number of days, it takes B to do the same piece of work is ……… |
A. | 6 days |
B. | 6 ¼ days |
C. | 7 ½ days |
D. | 8 days |
Answer» D. 8 days | |