Q: A, B and C can complete a work in 10, 15 and 20 days respectively. A and B start it together. B is replaced by C after 2 days. A leave it after one more day. In how many days work was completed? |
| A. | 13 |
| B. | \(13 {1 \over 13 }\) |
| C. | \(18 {4 \over 3 }\) |
| D. | 18 |
| Answer» C. \(18 {4 \over 3 }\) | |