MCQOPTIONS
Saved Bookmarks
1. |
Q: 12 men complete a work in 9 days. After they have worked for 6 days, 4 more men join them. How many days will they take to complete the remaining work ? |
A. | 2 days |
B. | 2.5 days |
C. | 2.25 days |
D. | 3 days |
Answer» D. 3 days | |