| 1. |
_________ plan and manage the project on a day-to-day basis for this stage _________ define the coordination, control activities and identify the suitable personnel to carry them out. |
| A. | Project coordinators, stage teams |
| B. | Stage managers, project coordinators |
| C. | Stage teams, key stakeholders |
| D. | Stage managers, key stakeholders |
| Answer» C. Stage teams, key stakeholders | |