				| 1. | 
                                    Pick up the incorrect statement from the following$? | 
                            
| A. | An activity of the project is denoted by an arrow on the net work | 
| B. | The tail of the arrow indicates the start of the activity | 
| C. | The head of the arrow indicates the end of the activity | 
| D. | The arrows are drawn (to scale from) left to right | 
| Answer» E. | |