| 1. |
%_Pick up the correct statement from the following_% |
| A. | If the float is positive and the activity is delayed by a period equal to its total float, the completion of project in not delayed |
| B. | If the float of an activity is negative, delay in its performance is bound to delay the completion of project |
| C. | If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project |
| D. | All of the above |
| Answer» E. | |