1. |
Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it |
A. | Consumes time, but no resources |
B. | Consumes resources but no time |
C. | Consumes neither time nor resources |
D. | Is a dangling event |
Answer» D. Is a dangling event | |