MCQOPTIONS
Saved Bookmarks
1. |
Performing an analysis of risks and conditions to prioritize their impacts on project objectives is known as |
A. | Quantitative Risk Analysis |
B. | Qualitative Risk Analysis |
C. | Risk Management Planning |
D. | Risk Identification |
Answer» C. Risk Management Planning | |