P, Q, R and S are working on a project. Q can finish the task in 25 days, working alone for 12 hours a day. R can finish the task in 50 days, working alone for 12 hours per day. Q worked 12 hours a day but took sick leave in the beginning for two days, R worked 18 hours a day on all days. What is the ratio of work done by Q and R after 7 days from the start of the project? |
A. | 10:11 |
B. | 11: 10 |
C. | 20: 21 |
D. | 21: 20 |
Answer» D. 21: 20 | |