P, Q and R get Rs. 10800 for doing a work in 18 days. P and R get Rs. 3760 for doing the same work in 10 days, while Q and R get Rs. 6080 for doing the same work in 20 days. Find the amount received by R per day?

A. Rs. 95
B. Rs. 126
C. Rs. 80
D. Rs. 200
Answer» D. Rs. 200