1. |
P, Q and R can do some work in 11 days, 20 days and 55 days respectively. In how many days can the work be done, if P gets the assistance of Q and R on alternate days? |
A. | 7 |
B. | 9 |
C. | 8 |
D. | 10 |
Answer» D. 10 | |