| 1. |
P can finish a work in 18 days. Q can finish the same work in 15 days. Q worked for 10 days and left the job. how many days does P alone need to finish the remaining work? |
| A. | 8 |
| B. | 6 |
| C. | 4 |
| D. | 2 |
| Answer» C. 4 | |