P can do a work in X days. He finished 1/6 of the entire work and then Q alone finished the rest in 15 days. If together they can finish half of the work in 45/8 days, then find the value of X?A. 90/11B. 30C. 42D. 32/8

A. B
B. D
C. C
D. A
Answer» B. D