1. |
P can do a piece of work in 18 days and Q can do in 22 days, with the help of C, they finish the work in 6 days. How long will it take R to finish the work? |
A. | 17days |
B. | 18days |
C. | 16 ½ days |
D. | 17 ½ days |
Answer» D. 17 ½ days | |