1.

P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?

A. 5 5/11 days
B. 5 6/11 days
C. 6 5/11 days
D. 6 6/11 days
Answer» B. 5 6/11 days