| 1. |
P and Q need 8 days to complete a work. Q and R need 12 days to complete the same work. But P, Q and R together can finish it in 6 days. How many days will be needed if P and R together do it? |
| A. | 7 |
| B. | 8 |
| C. | 9 |
| D. | 10 |
| Answer» C. 9 | |