P and Q can do a work in 30 days. Q and R can do the same work in 24 days and R and P in 20 days. They started the work together, but Q and R left after 10 days. How many days more will P take to finish the work? |
A. | 10 |
B. | 8 |
C. | 18 |
D. | 19 |
Answer» D. 19 | |