1.

P and Q can do a work in 30 days. Q and R can do the same work in 24 days and R and P in 20 days. They started the work together, but Q and R left after 10 days. How many days more will P take to finish the work?

A. 10
B. 8
C. 18
D. 19
Answer» D. 19