P and Q can complete a job in 6 and 8 days individually. They both finish the job with the help of R in 3 days. How much wages are to be paid to R. if the total wages are Rs. 3200? |
A. | Rs. 375 |
B. | Rs. 400 |
C. | Rs. 1200 |
D. | Rs. 320 |
Answer» C. Rs. 1200 | |