1. |
P and Q can complete a job in 12 days and 16 days respectively. They work together for 4 days. What portion of work is left for completion? |
A. | 3/4 |
B. | 6/7 |
C. | 5/12 |
D. | 7/12 |
Answer» D. 7/12 | |