

MCQOPTIONS
Saved Bookmarks
1. |
P alone can complete a piece of work in 6 days. Work done by Q alone in one day is equal to one-third of the work done by P alone in one day. In how many days can the work be completed if P and Q work |
A. | 4(3/4) |
B. | 4(1/2) |
C. | 4 |
D. | 5 |
Answer» C. 4 | |