1. |
P alone can complete a piece of work in 12 days and Q can complete the same work in 18 days. With the help of R, all three finish the work in 6 days. In how many days can R alone complete the work? |
A. | 36 days |
B. | 28 days |
C. | 25 days |
D. | 30 days |
Answer» B. 28 days | |