1.

Milena and Mashuka can together complete a work in 36 days. However, Mashuka works alone and left the work after completing 2/5 part of work and then Milena starts work and completes the rest of the work. As a result both completes the work in 78 days. If Mashuka is more efficient than Milena then time(in days) taken by Milena to complete the work alone:

A. 96
B. 100
C. 90
D. 102
Answer» D. 102