

MCQOPTIONS
Saved Bookmarks
1. |
Match List 1 and List 2 and select the correct answer using the codes given below:List-1 List-2 A. Cut-off trench of a dam to be constructed across the flowing river 1. Cellular sheetpile cofferdam B. Shallow foundation of a bridge pier foundation work 2. Embankment type cofferdam C. Sequential repetition of underwater foundation work 3. Single wall sheetpile cofferdam D. Control of groundwater to prevent entry into a deep excavation 4. Floating steel cylinder cofferdam |
A. | A – 4, B – 3, C – 2, D - 1 |
B. | A – 2, B – 1, C – 4, D - 3 |
C. | A – 2, B – 3, C – 1, D - 4 |
D. | A – 3, B – 4, C – 2, D - 1 |
Answer» C. A – 2, B – 3, C – 1, D - 4 | |