1. |
Manju takes 16 days to complete a work. If she works with her friend Jenny they complete it in 12 days. How many days will it take for Jenny to complete the work alone? |
A. | 48 |
B. | 32 |
C. | 36 |
D. | 24 |
Answer» B. 32 | |