Mahesh asked 32 men to build his house in 20 days. 80% of the work got completed in just 12 days. So Mahesh removed some workers. Now how many persons does he need to complete the remaining work in decided time? |
| A. | 12 |
| B. | 20 |
| C. | 32 |
| D. | 16 |
| Answer» B. 20 | |