M can complete a piece of work in 10 days. N is 33.33% less efficient than M. calculate the number of days required to both to complete the work? |
| A. | 6 days |
| B. | 8 days |
| C. | 11 days |
| D. | 13 days |
| Answer» B. 8 days | |