M and N working separately can complete a job in 6 and 12 hours respectively. If they work for an hour alternately M starting at 10:00 AM when will the job be done? |
| A. | 2:00 PM |
| B. | 8:00 PM |
| C. | 7:00 PM |
| D. | 6:00 PM |
| Answer» E. | |