

MCQOPTIONS
Saved Bookmarks
1. |
Let ‘x’ be the number of days taken by B alone to finish the whole work Then, A alone will finish the whole work in 3x/4 × 2 days = 3x/2 days. Then, working together, 3x/2 × x/3x/2 + |
A. | 30 days |
B. | 35 days |
C. | 40 days |
D. | 45 days |
Answer» B. 35 days | |