It was estimated that 52 men can complete a strip in a newly constructed highway connecting cities P and Q in 10 days. Due to an emergency, 12 men were sent to another project. How many numbers of days, more than the original estimate, will be required to complete the strip? |
| A. | 3 days |
| B. | 5 days |
| C. | 10 days |
| D. | 13 days |
| Answer» B. 5 days | |