1.

In normal circumstances where ambient temperature does not fall below 15°C, for a properly cured reinforced concrete slabs spanning up to 4.5 metre span cast using ordinary Portland cement, the props provide can be removed only after a minimum period of

A. 3 days
B. 7 days
C. 14 days s
D. 21 days
Answer» C. 14 days s