In normal circumstances where ambient temperature does not fall below 15°C, for a properly cured reinforced concrete slabs spanning up to 4.5 metre span cast using ordinary Portland cement, the props provide can be removed only after a minimum period of |
A. | 3 days |
B. | 7 days |
C. | 14 days s |
D. | 21 days |
Answer» C. 14 days s | |