MCQOPTIONS
Saved Bookmarks
| 1. |
In an assembly line for assembling toys, five workers are assigned tasks which take times of 10, 8, 6, 9 and 10 minutes respectively. The balance delay for line is |
| A. | 43.3% |
| B. | 14.8% |
| C. | 14.0% |
| D. | 16.3% |
| Answer» D. 16.3% | |