| 1. |
In an assembly line for assembling the engine, six workers are assigned tasks that take 22, 24, 26, 27, 25 and 26 minutes respectively. The balance delay for the line is: |
| A. | 7.4% |
| B. | 14.8% |
| C. | 7% |
| D. | 10.3% |
| Answer» B. 14.8% | |