1.

In a casting process, a mould of dimension 60 cm x 30 cm x 14 cm is to be filled by liquid metal using the top pouring method. The liquid metal height above the top surface of the mould is 14 cm and the area of the gate is 6 cm2. The time taken to fill the mould will be:

A. 32 s
B. 12 s
C. 25.34 s
D. 28.28 s
Answer» D. 28.28 s