If you are planning a project in SAP PS using CJ40 Work Breakdown Structure, at which of the following locations can you find the values used in the planning? |
| A. | RPSCO table |
| B. | COSS & COSP tables |
| C. | BPEJ table |
| D. | None of the mentioned |
| Answer» C. BPEJ table | |