| 1. |
If TL is the largest allowable event occurrence time, total activity slack (s) is equal to |
| A. | Latest start time earliest start time |
| B. | Latest finish time earliest finish time (EFT) |
| C. | TLEFT |
| D. | All of the above |
| Answer» E. | |