1.

If the peak load on a power plant having a capacity of 100 MW is 70 MW during a given week and the energy produced is 58, 80,000 kWh, the capacity factor for the plant for the week will be ___________________

A. 35%
B. 50%
C. 70%
D. 65%
Answer» B. 50%