1.

If the peak load on a power plant having a capacity of 100 MW is 70 MW during a given week (7-days), and the energy produced is 5880000 kWh, the capacity factor (in %) for the plant for the said week is

A. 35
B. 50
C. 65
D. 30
E. 70
Answer» B. 50