1. |
If the peak load on a power plant having a capacity of 100 MW is 70 MW during a given week (7-days), and the energy produced is 5880000 kWh, the capacity factor (in %) for the plant for the said week is |
A. | 35 |
B. | 50 |
C. | 65 |
D. | 30 |
E. | 70 |
Answer» B. 50 | |