If P and Q together can do a job in 15 days, Q and R together can do it in 12 days and P and R together can do the same in 20 days, then in how many days will the job be completed, if all the three work together? |
A. | 4 days |
B. | 6 days |
C. | 10 days |
D. | 14 days |
Answer» D. 14 days | |